I'm back from vacation and back with another summer update for those of you who are wondering how things are going.
- All of Cabot School was moved out last week.
- On Tuesday, Wednesday and Thursday of this week, the moving company moved our supplies and furniture to Nevada St. We are now officially moved in...
- There's still lots of work to be done here...they are installing lockers on Saturday, patching holes and painting walls in some rooms, finishing renovation and A/C work, installing storage in classrooms, etc. And we have TONS of unpacking to do! Work will continue throughout the remainder of August. You can see the work that has continued in a number of different areas in the photos below.
I'll be in touch soon with more details and my traditional summer letter.
Office Supply Room: old countertops and furniture have been dismantled/removed:
Staff Room/DAD Space - The wall partition has been completed and plumbing has been installed. The wall intentionally only covers a portion of the space to allow for natural light to come in from the rear wall. Cabinet installation is next for this space.
Seyferth: Photos from inside the room and from the hallway:
Literacy Space:
Sandison:
A/C Units - Many of the AC units have been installed in classrooms. Not all of them are connected yet. This work is ongoing.
Kiln Room Door Installation (Chatfield):
Sink/Plumbing Installation (Gower):
Bus Loop: